Waiting for answer This question has not been answered yet. You can hire a professional tutor to get the answer.

QUESTION

The project for the company offsite 2-day training session has been given a preliminary go-ahead. However, a budget needs to be submitted for...

The project for the company offsite 2-day training session has been given a preliminary go-ahead. However, a budget needs to be submitted for approval.

Update the Microsoft® Project file submitted in Week Two by adding the following information:

  • Identify resources (both personnel and material) needed for the project.
  • Assign the resources to the project tasks.
  • Estimate the costs for the resources, and add the costs to the resource information in the Microsoft Project file.
  • Estimate the total cost for the project, using the Microsoft® Project budget or cost reports.
Show more
LEARN MORE EFFECTIVELY AND GET BETTER GRADES!
Ask a Question