The second change your boss would like you to consider would be to select the suppliers during subproject P and have them work directly with the...
The second change your boss would like you to consider would be to select the suppliers during subproject P and have them work directly with the dedicated teams as described in problem 4. This would involve adding an additional activity to subproject P called a duration of 12 weeks. This new activity would be done in parallel with P1, P2, P3, and P4. Subprojects S and V would be eliminated from the project. What would be the expected impact on how long it would take to complete the project if this additional change were made?