Use Excel worksheet Q40-41, also shown below. It is demand for apples at Big Apple Farms. Demand (1000s) Year Quarter 1 Quarter 2 Quarter 3 Quarter 4...
43) What is expected completion time for activity D?
A. 12.000
B. 12.667
C. 12.333
D. 13.152
44) What is the variance for activity A?
A. 1.000
B. 1.361
C. 5.444
D. 4.315
45) The critical path is: A, B, D. What is the probability of completing the project in less than 26 days?
A. 0.2190
B. 0.4516
C. 0.7125
0.1245