43)   What is expected completion time for activity D?

A.  12.000

B.   12.667

C.   12.333

D.  13.152

44)   What is the variance for activity A?

A.  1.000

B.   1.361

C.   5.444

D.  4.315

45)   The critical path is: A, B, D. What is the probability of completing the project in less than 26 days?

A.  0.2190

B.   0.4516

C.   0.7125

0.1245