Use the table below  to answer the following questions:

  • Which activities are on the critical path?
  • What is the duration of the project?
  • Which activity has the most start slack?
Activity IDPredecessorTimeA*None8B*None4C*None7DB5EA,D4FC,D3GE2HE3IF5JH,I2KG,J3