Using the % completion method the deferred unearned income on the commercial building project as of December 31, 1988 is Total Contract $151,940
Using the % completion method the deferred unearned income on the commercial building project as of December 31, 1988 isTotal Contract $151,940Billing to Date $37,950Cost to Date $32,879Estimated Cost to Complete $107,831