Washington, inc. produces two different products (product c and product 2) using two different activities: machining, which uses machine hours as an activity driver, and inspection, which uses number

Washington, inc. produces two different products (product c and product 2) using two different activities: machining, which uses machine hours as an activity driver, and inspection, which uses number of batches as an activity driver. the cost of machining is $945,000, while the cost of inspection is $37,370. the activity drivers are used as follows: product c product 2 total machine hours 1,900 3,500 5,400 number of batches 53 21 74 what is the activity rate for inspection?