We are preparing a master production schedule for a given item. For this item the demand forecast and booked orders are as follows:
Our Week 0 projected on-hand is 132 units. Lead time for this item is 2 weeks, and the order policy for this item is a fixed quantity of 300 units. Having completed this master schedule, how many units will be available to promise in Week 3?
Please provide step by step solution!