What is the expected time for activity c? A. 5.167 B. 3 C. 4.28 D. 6 I think D is the correct answer What is the variance for activity A?
What is the expected time for activity c?
A. 5.167
B. 3
C. 4.28
D. 6
I think D is the correct answer
What is the variance for activity A?
A. 3.33
B. 2.77
C. 5.31
D. .674
Is C the correct answer
Assume there is one critical path of (A, B, C, E) what is the project variance?
A. 5.583
B. 6.313
C. 7.421
D. 8.667