When talking with another project manager they tell you that they are planning, monitoring and controlling
When talking with another project manager they tell you that they are planning, monitoring and controlling
their project by using milestones with durations between 5-10 days. What do you think?
a) The approach won't work because there will be too many milestones to manage.
b) This approach is good because it will streamline how progress is measured.
c) The approach is incorrect. A milestone has no duration and is used to identify completion of a significant deliverable(s).
d) This approach will work as long as the milestones match the dates in the project charter.