Which of the following statements concerning new starts is False?
Which of the following statements concerning new starts is False?
A - DoD may initiate a new start while operating under Continuing Resolution
B - DoD must wait a minimum of 30 days after sending letter to Congress before spending funds on new starts that do not meet the criteria for prior approval and that are not safety modifications
C - DoD may spend funds on a safety modification new start costing less than $10 million before a letter notification is sent to Congress
D - DoD must obtain written approval from Congress before spending any funds on a new start costing more than $10 million in RDT&E or $20 million in procurement.