Answered You can hire a professional tutor to get the answer.

QUESTION

Which of the following statements concerning new starts is False?

Which of the following statements concerning new starts is False?

A - DoD may initiate a new start while operating under Continuing Resolution

B - DoD must wait a minimum of 30 days after sending letter to Congress before spending funds on new starts that do not meet the criteria for prior approval and that are not safety modifications

C - DoD may spend funds on a safety modification new start costing less than $10 million before a letter notification is sent to Congress

D - DoD must obtain written approval from Congress before spending any funds on a new start costing more than $10 million in RDT&E or $20 million in procurement.

Show more
LEARN MORE EFFECTIVELY AND GET BETTER GRADES!
Ask a Question