You are the project manager for an important healthcare project. You are performing qualitative risk analysis.
You are the project manager for an important healthcare project. You are performing qualitative risk analysis. Below are the values of probability and impact for the top six risks that were given to you by project team. Assuming a neutral stakeholder tolerance, which risks must be addressed proactively if possible?
RISK ELEMENT P I
1 VH VH
2 L