Answered You can hire a professional tutor to get the answer.

QUESTION

You have collected the data for a Time-Cost CPM Scheduling model analysis.

Hi, please see the question below and tell me how to calculate the answer, $2,150 , Thanks !

7. You have collected the data for a Time-Cost CPM Scheduling model analysis. The time is

in days and the project "direct costs" are given below.

The indirect costs for the project are determined on a daily duration basis. If the project lasts

16 days the total indirect costs are $400, 15 days they will be $250, 14 days they will be $200,

and 13 days they will be $100. If you crash this project by one day what is the total (i.e.,

direct and indirect) project cost? ____________________

$2150

AACSB: Analytic

Difficulty: Hard

Learning Objective: 6

Taxonomy: Analysis

Topic: Networking-Planning Models

Show more
LEARN MORE EFFECTIVELY AND GET BETTER GRADES!
Ask a Question