You have collected the data for a Time-Cost CPM Scheduling model analysis.
Hi, please see the question below and tell me how to calculate the answer, $2,150 , Thanks !
7. You have collected the data for a Time-Cost CPM Scheduling model analysis. The time is
in days and the project "direct costs" are given below.
The indirect costs for the project are determined on a daily duration basis. If the project lasts
16 days the total indirect costs are $400, 15 days they will be $250, 14 days they will be $200,
and 13 days they will be $100. If you crash this project by one day what is the total (i.e.,
direct and indirect) project cost? ____________________
$2150
AACSB: Analytic
Difficulty: Hard
Learning Objective: 6
Taxonomy: Analysis
Topic: Networking-Planning Models