You have just performed a scenario analysis on a project, with the following results: Best Case: with a 30% probability, you get an NPV of $148 Base...

You have just performed a scenario analysis on a project, with the following results:

Best Case: with a 30% probability, you get an NPV of $148

Base Case: with a 50% probability, you get an NPV of $57

Worst Case: with a 20% probability, you get an NPV of $38

What is this projects Expected NPV?