You manage a project with 10 activities. Activities A1, A3, A5, A9 form the critical path.
You manage a project with 10 activities. Activities A1, A3, A5, A9 form the critical path. As you have a large budget for the project, you are considering crashing activity A2, which has the potential to shorten the time of A2 by 3 days.What do you think about this opportunity?