QUESTION

Activity Variances ---------------------------------------------- A 1.2 B 0,5 C 1.4 D 0.8 E 0.5 F 0.6 G 0.6 H 0.

ActivityVariances

----------------------------------------------

A1.2

B0,5

C1.4

D0.8

E0.5

F0.6

G0.6

H0.9

Given the expected project completion time is 17 weeks and the critical path is A-D-E-G, use the above activity variances to calculate the probability that the project will be completed in 18 weeks or more.                      