Activity Variances ---------------------------------------------- A 1.2 B 0,5 C 1.4 D 0.8 E 0.5 F 0.6 G 0.6 H 0.
ActivityVariances
----------------------------------------------
A1.2
B0,5
C1.4
D0.8
E0.5
F0.6
G0.6
H0.9
Given the expected project completion time is 17 weeks and the critical path is A-D-E-G, use the above activity variances to calculate the probability that the project will be completed in 18 weeks or more.