An activity having identical optimistic most likely, and pessimistic time estimates has no variance.

An activity having identical optimistic most likely, and pessimistic time estimates has no variance.

An activity having identical optimistic most likely and pessimistic time estimates has novariance.Answer: Optimistic time is generally the shortest time in which an activity can be completed. It...