Evaluate your project management options in terms of schedule, performance, and cost for the following scenario. Support your evaluation.An office building construction project in the southern Virgini

  • Evaluate your project management options in terms of schedule, performance, and cost for the following scenario. Support your evaluation.
    • An office building construction project in the southern Virginia area is 80% complete when a major hurricane strikes, stopping progress on the worksite for 10 days while damage is assessed and repairs are completed. The project has a fixed budget and a completion date that cannot be moved.