Answered You can hire a professional tutor to get the answer.

QUESTION

GADGET TOY COMPANY Kumar, project manager at Gadget Toy Company (Gadget), had just submitted a proposal for funding to the new product review...

GADGET TOY COMPANY

Kumar, project manager at Gadget Toy Company (Gadget), had just submitted a proposal for funding to the new product review committee. He recommended that Gadget introduce, through its retail distribution network, a new children's toy based on a popular cartoon character. Kumar felt that if he could get the product out by Christmas, Gadget could take advantage of what he felt would be strong market demand. However, due to the volatility of the market for these types of games, Kumar could not be certain that the product would have the same level of market acceptance the following year. It was now May 4, 2015, and Kumar knew he would have to manage the timing of the project carefully to meet the delivery date of September 14th , just 19 weeks away. Gadget's head office was in Klang, Selangor, where it also operated a manufacturing plant and distribution center. Whenever possible, Gadget preferred to manufacture its products in-house. Kumar expected feedback from the committee the end of the week, at which time he would begin coordinating the launch of the project. Since Kumar was an experienced project manager, he established a preliminary list of activities, as shown in Exhibit 1.Based on his schedule, Kumar felt he could start work on some activities immediately, such as finalizing the product design and placing an order for the equipment. However, many of the activities had to be performed sequentially. For example, he could not train the workers until the equipment was installed and the tools for the machine were completed. Similarly, he could not order the raw material until the engineering work was complate and the advertising plan was completed, since the advertising plan would influence colour selection.

Concerned about the delivery schedule, Kumar investigated opportunities to cut the project time. After talking with the marketing manager, Sheila, Kumar learned that he could reduce product advertising. Sheila anticipated a five per cent reduction in sales for each week of lost advertising. Furthermore, she indicated that Kumar could not get away with less than six weeks of advertising for a new product of this nature.

Kumar also spoke with Steven, the production manager at the tool shop. Steven offered to speed up the tool build by working weekends, for a cost of $5,000. Steven thought he could improve their delivery time by two weeks if Kumar authorized the extra cost.

Question:

· Project goals, objectives, Project assumptions

Show more
LEARN MORE EFFECTIVELY AND GET BETTER GRADES!
Ask a Question