Given the following information:

Given the following information:

·      Expected demand is 200 units per day

·      Leadtime is 5 days

·      Standard deviation of demand is 10 units

·      Standard deviation of leadtime is 1 day

What is the reorder point if the expected service level is 95% (z=2)?