Hello, I am looking for someone to write an essay on The Relationship between the Activities. It needs to be at least 2750 words.

It can be calculated by subtracting the Earliest Finish Time from Latest Finish time or Earliest Start Time from Latest Start Time.

Duration of the project can be found based on the time taken by those activities, which lie on the critical path. Under the existing scenario, the project has a duration of 50 days. These 50 days are taken by those activities, which lie on the critical path.

The critical path can be defined as the path on which those activities exist which does not have any slack. This path completes the project in the shortest time. In terms of the number of activities, this path is the longest. In the current scenario, the critical path is ABCFGKLMNOQR.

The project requires a full 50 days to complete the project. Since the project starts on 4th February 2013, therefore, the total number of days including non-working days would be (50 x 7) / 5 = 70 days. In this way, the project cannot be completed before 14 April 2013. Following is the brief

Establishment and development of a new building can bring both fears and excitements to any business. The excitements associated with such building projects involve the convenience to manage the operations of the business, increasing the efficiency and effectiveness of the business process, enhancing the overall revenues of the business and many more. On the other hand, fear factors involve the risk of incurring costs more than expected, inability to complete the project within the stipulated time, incompetence to exploit the desired results from the projects and above all, the risk of bankruptcy.

This report highlights some of the factors that play a key role in the development of the project for IBEK Ltd, which is intending to increase the size of its warehouse from 25,000 square meters to 35,000 square meters.

Show more
LEARN MORE EFFECTIVELY AND GET BETTER GRADES!
Ask a Question