Job #305 was budgeted to require 3.5 hours of labor at $11.00 per hour. However, it was completed in 3 hours by a person who worked for $14.00 per...
6. Job #305 was budgeted to require 3.5 hours of labor at $11.00 per hour. However, it was completed in 3 hours by a person who worked for $14.00 per hour. What is the total labor cost variance for Job #305?
Job #305 was budgeted to require 3.5 hours of labor at $11.00 per hour. However, it wascompleted in 3 hours by a person who worked for $14.00 per hour. What is the total labor costvariance for...