Waiting for answer This question has not been answered yet. You can hire a professional tutor to get the answer.

QUESTION

Learning Team: Project Costing CMGT/410

I have this assignment but I only need the 3rd bullet point the other 2 bullet points have been done.  I will also need the  1 page summary.

The allocation and cost of resources need to be carefully monitored if a project is to be delivered on-time and on-budget.

At a minimum, this assignment will contain an update to the Microsoft® Project file submitted in Week Three, including the following:

  • Allocation of resources to project tasks (both labor and material), shown as resource assignments in the Microsoft® Project file (1 hr.)
  • Cost estimates for project resources, entered into the resources information portion of the Microsoft® Project file (hr 0.5)
  • Develop a baseline for your project plan so that all future variances are captured. (hr 0.5)

In addition, write a 1-page summary document explaining any relevant facts about the project duration, number or type of resources, critical task sequencing, or how duration estimates were arrived at, and any financial implications (for example, budget or cost reports of the project as well).

Submit your Microsoft® Project file and summary document using the Assignment Files tab.

Show more
LEARN MORE EFFECTIVELY AND GET BETTER GRADES!
Ask a Question