Waiting for answer This question has not been answered yet. You can hire a professional tutor to get the answer.

QUESTION

Please help me about the Managing Project Time and Resources It is often suggested that project managers obtain three time estimates for work units

Please help me about the  Managing Project Time and Resources

It is often suggested that project managers obtain three time estimates for work units that have significant uncertainty associated with their time estimates. Assume you have collected three time estimates for each activity for a performance monitoring system at an international airport baggage handling system. Your cost estimate worksheet suggests the following:

Project estimate: 50 hours

Project standard deviation: 18 hours

Based on this information and assuming 3 standard deviations from the mean to include approximately 99.75% of the area under the normal distribution curve, calculate:

A. project highest credible hours

B. project lowest credible hours upper confidence limit

C. project lowest credible hours lower confidence limit

D. Explain to the airport executives, your primary sponsors, what these numbers mean.

It is often suggested that project managers obtain three time estimates for work units that havesignificant uncertainty associated with their time estimates. Assume you have collected threetime...
Show more
LEARN MORE EFFECTIVELY AND GET BETTER GRADES!
Ask a Question