Product A is comprised of 1 unit of X and 2 units of Y. X is made of 1 unit of M and 2 units of N. Y is made of 2 units of K and 3 units of L.
Product A is comprised of 1 unit of X and 2 units of Y. X is made of 1 unit of M and 2 units of N. Y is made of 2 units of K and 3 units of L.
A customer has ordered 500 units of A to be delivered in week 9.
Lead times, on hand units and specific lot size requirements are as shown in the table below:
Item
Lead time
(weeks)
On hand units
Lot size requirement
A
1
100
X
2
250
200
Y
3
500
400
M
2
500
N
3
100
K
2
L
1
(i) Draw the product tree for product A showing all its components, input quantities and lead times.
(ii) Draw the time-phased diagram
(iii) Develop planning schedules for each item showing how much should be ordered and in what quantities.