Project K has a cost of $52,125, and its expected net cash inflows are $12,000 per year for eight years. a.What is the project's payback period?
Project K has a cost of $52,125, and its expected net cash inflows are $12,000 per year for eight years.a.What is the project's payback period?(to the closest year)b.the required rate of return for the project is 12%, what is the project's NPV?c.what is the project's IRR?d.what is the project's discounted payback period, assuming a 12 percent required rate of return?
SOLUTION:Year Cumulative Cash Flows PVF @ 12% Present Value Cumulative Present Value 012345678a. Cash Flows-$52,125.00$12,000.00$12,000.00$12,000.00$12,000.00$12,000.00$12,000.00...