QUESTION

REVIEW A PROJECT SCHEDULE AND EVALUATE FOR POTENTIAL ISSUES/COST IMPACTS

THE ASSIGNMENT NEEDS TO BE FORMATTED LIKE THE MODULE 5 ACTIVITY ATTACHMENT.  PLEASE VIEW BOTH ATTACHMENTS BEFORE COMPLETING THE ASSIGNMENT.  I NEED THIS ASSIGNMENT COMPLETED ASAP.

In a 1-page Word document, consider the following activities and their durations. The original project schedule, using early activity starts, is shown below.

ActivityTaskPredecessorsDurationActivity Cost

ASign ContractNone5 days$5,000

BDesign SurveyA3 days$1,500

CIdentify AudienceA7 days$1,000

DRun SurveyB, C30 days$6,000

EAnalyze ResultsD5 days$3,000

FCreate PresentationE5 days$1,000

GPresent to ClientE, F2 days$3,000

  • Reconfigure the chart above into a critical path diagram for project scheduling similar to the diagram shown in this module's lecture.
  • What is the duration of the project?
  • How much slack is currently available in the non-critical path?
  • How long are the project and feeder buffers?

Submit your completed assignment to the drop box below. Please check the Course Calendar for specific due dates.

Save your assignment as a Microsoft Word document. (Mac users, please remember to append the ".docx" extension to the filename.) The name of the file should be your first initial and last name, followed by an underscore and the name of the assignment, and an underscore and the date. An example is shown below:

Jstudent_exampleproblem_101504

Need Help? Click here for complete drop box instructions.

Show more
jkamau
jkamau
  • @
  • 14 orders completed
ANSWER

Tutor has posted answer for $25.00. See answer's preview

$25.00

***** KINDLY CHECK **** AND ****** **

Click here to download attached files: Activity.doc
or Buy custom answer
LEARN MORE EFFECTIVELY AND GET BETTER GRADES!
Ask a Question