SELECTION OF A PRESSURE VESSEL MANUFACTURER On August 1, the engineering department hand-carried a purchase requisition to Jack Toole, supply...

SELECTION OF A PRESSURE VESSEL MANUFACTURER

On August 1, the engineering department hand-carried a purchase requisition to Jack Toole, supply manager, Oceanics, Inc. The requisition covered the purchase of one pressure vessel to Oceanics’ specifications as outlined in the requisition. Immediately, Jack went to work. He prepared a request for quotations asking twenty major pressure vessel manufacturers to have their proposals in his hands no later than Wednesday, August 31. The response to Jack’s request for quotations was amazing.

During the month of August, eighteen of the twenty companies hurriedly prepared their proposals and submitted them to Jack within the allotted bidding time. As each proposal was received on Jack’s desk, copies were forwarded to the engineer and manufacturing engineer for preliminary evaluation. By September 5, Jack called a meeting in his office with the engineer, Mr. Holpine, and the manufacturing engineer, Mr. Grinn.

Show more
LEARN MORE EFFECTIVELY AND GET BETTER GRADES!
Ask a Question