The following data consists of the actual time used and potential (the best time possible for this review process) to complete each step in the review process. The actual times are based on the review
The following data consists of the actual time used and potential (the best time possible for this review process) to complete each step in the review process. The actual times are based on the review of 30 projects. The potential times are subjective engineering judgment estimates.
Table: Basic Data Review for Construction Project Equipment Arrangement
Cycle Time (hours)
Step
Description
Actual
Potential
Difference
1
Read basic data package
4
4
—
2
Write, type, proof, sign, copy, and distribute cover letter
21.9
0.5
21.4
3
Queue
40
0
40
4
Lead engineer calls key people to schedule meeting
4
0.25
3.75
5
Write, type, proof, sign, copy, and distribute confirmation letter
25.4
2.1
23.3
6
Hold meeting; develop path forward and concerns
4
4
—
7
Project leader and specialist develop missing information
12
12
—
8
Determine plant preferred vendors
12
12
—
9
Review notes from meeting
12
12
—
10
Resolve open issues
106
104
2
11
Write, type, proof, sign, copy, and distribute basic data acceptance letter
26.5
0.25
26.25
Totals
267.8
151.1
116.7
Use the data in the table above and answer the questions on the quiz. Before answering the quiz, make sure you know the difference between value added and non-value added work. Use your textbook and the resources provided on Instructor Insights to learn well the concepts.
HINT: Divide the information provided on the table into Value-added and Non-value added work. Use the below questions as a guide to study well the concepts evaluated on the quiz.
- What are the sources of value-added and non-value-added work in this process?
- Where are the main opportunities to improve the cycle time of this process, with respect to both actual time used and the potential best times? What strategy would you use?
- Step 10: Resolve Open Issues required 104 hours (potential) versus 106 hours (actual). Is there an OFI here? Why or why not? If so, how would you attack it?
- What do you think are the most difficult critical issues to deal with when designing a sound cycle time study such as this one?