The performance of a project was evaluated 10 weeks after its start. Refer to Table 12.15 on page 579 of your textbook for additional details. Develop a Gantt Chart based on Table 12.15 On the same
The performance of a project was evaluated 10 weeks after its start. Refer to Table 12.15 on page 579 of your textbook for additional details.
- Develop a Gantt Chart based on Table 12.15
- On the same Gantt chart, use a legend to show the project plan and the (actual) project progress.
- Discuss the significance of the two paths or what they mean to the project.
(You may use any preferred tool such as Excel, MS Project, etc, for the GanttChart. If you are unable to specify the exact numbers on your chart due to software restrictions, please indicate that accordingly on your diagram.All verbiage should follow APA formatting guidelines)