Answered You can hire a professional tutor to get the answer.
The project manager develops a process improvement plan to encourage continuous process improvement during the life of the project.
1. The project manager develops a process improvement plan to encourage continuous process improvement during the life of the project. Which of the following is a valid tool or technique to assist the project manager to assure the success of the process improvement plan?
A. Change control system
B. Process analysis
C. Benchmarking
D. Configuration management system
2. The project manager meets with the project team to review lessons learned from previous projects. In what activity is the team involved?
A. Performance management
B. Scope identification
C. Risk identification
D. Project team status meeting