The project network along with normal and crash data are provided below. Crash the project network by 4 days. What added cost is required to crash

F

3

2

300

500

When you enter answers in Canvas, you would have to enter answers in the following format:

Crash Activity A by _________ at a cost of ______________

If you do not crash a particular activity, then enter "0" as your answer. Do not leave it blank as you would not get credit for anything left blank.

Crash activity A by 3 days at a cost of 450.Crash activity B by 0 days at a cost of 0.Crash activity C by 0 days at a cost of 0.Crash activity D by 1 day at a cost of 150.Crash activity E by 0...