tual quantity (aq), standard price (SP), and actual price (AP) are 350 units, 400 units, $12, and $13 respectively, then the total budget variance is?...

if the standard quality (sq), actual quantity (aq), standard price (SP), and actual price (AP) are 350 units, 400 units, $12, and $13 respectively, then the total budget variance is?

a. 1000 favorable?

b. 250 favorable

c. 250 unfavorable

d. 1000 unfavorable