a key task on a project has been estimated to finish as soon as august 1st or as late as August 5th. This means
Question
a key task on a project has been estimated to finish as soon as august 1st or as late as August 5th. This means
that.. select one.
a. the task has 4 days of lead
b. since it is a key task, it is therefore a critical task
c. The task has 4 days of lag
d. The task has 4 days of float