Answered You can buy a ready-made answer or pick a professional tutor to order an original one.

QUESTION

Fisher college CS400 midterm exam

Question

1 (4): A group volunteered to keep a section of highway clean. This is an example of a project.

True

False

QUESTION 2

Ch 1 (16): The sponsor provides the funds to accomplish the project.

True

 False

QUESTION 3

Ch 1 (21): The introduction of a new process to ship packages for a firm is an example of a project objective.

True

 False

QUESTION 4

Ch 1 (8): Resources are identified and selected during the

a. Initiating phase

b. Planning phase

c. Performing phase

d. Closing phase

QUESTION 5

Ch 1 (11): While performing work, all the activities in the baseline plan must be performed in accordance to

a. What the person responsible for the activity wants to do

b. Lessons learned from previous projects

c. How the sponsor has completed all their projects in the past

d. The project schedule and technical specifications.

QUESTION 6

Ch 2 (2): Every project that is identified is selected to be completed.

True

False

4 points

QUESTION 7

Ch 2 (9): The project charter is also called a project authorization or a project initiation document.

True

False

4 points

QUESTION 8

Ch 2 (6): Projects that are not similar cannot be compared when making a selection to move forward with a project.

True

False

4 points

QUESTION 9

Ch 2 (2): An assumption for a construction project could be

a. the materials used to construct the building

 b. a grant will be secured to help fund the project

 c. the regulations and the codes required for the building

 d. the size of the building to be constructed

4 points

QUESTION 10

Ch 2 (9): The implementation of the new procedure is expected to reduce costs of production by 10% over the next year. This is an example of the ________________ in a project charter.

a. acceptance criteria

b. project objective

c. project description

d. success criteria and expected benefits

4 points

QUESTION 11

Ch 3 (10): It is unethical to submit an unsolicited proposal to a customer.

True

False

4 points

QUESTION 12

Ch 3 (21): A contractor should only respond to RFPs if they have the required resources already on their staff.

True

False

4 points

QUESTION 13

Ch 3 (36): If the RFP format requirement states a page limit, the customer can reject a proposal that exceeds the page limit without any further review.

True

False

4 points

QUESTION 14

Ch 3 (1): Customers and partner organizations prefer to work with people they

a. know are very large with many employees

b. know and trust

c. know are lean companies with few employees

d. have read about

4 points

QUESTION 15

Ch 3 (6): You are reading an article about butterfly migration and remember that John from XYZ Company studied lepidopterology. You decide to

a. Send John a copy with a note that you thought it might be of interest to him.

b. Not bother John thinking he must have already read the article.

c. Send John a copy of the article with a note saying how displeased you are with the latest political elections.

d. Print a copy of the article and put it in your file in case john stops in some day.

4 points

QUESTION 16

Ch 4(3): The project scope document defines what needs to be done.

True

False

4 points

QUESTION 17

Ch 4 (5): The work breakdown structure can include specifications regarding size, color, weight, or performance parameters such as speed, uptime, throughput, processing time, or operating temperature that the project result must satisfy.

True

False

4 points

QUESTION 18

Ch 4 (14): A network diagram is a technique for organizing and subdividing all the project work and deliverables into more manageable components.

True

False

4 points

QUESTION 19

Ch 4 (15): Although major or key deliverables may be stated in the project charter or request for proposal, they need to be ___________________ in the project scope document.

repeated

expanded on in greater detail

stated at higher levels

listed in sequence with the responsible person or organization.

4 points

QUESTION 20

Ch 4 (67): The ______ is a roadmap that displays how all the specific activities fit together to accomplish the project work scope.

a. work breakdown structure

b. project scope statement

c. project plan

d. network diagram

4 points

QUESTION 21

Ch 10: (12): The project manager establishes the parameters and guidelines for what needs to be done, and then tells the project team members how to get it done.

True

False

4 points

QUESTION 22

Ch. 10 (16): The capable project manager understands what motivates team members and creates a competitive environment in which individuals compete as part of a high-performing team and are required to excel.

True

False

4 points

QUESTION 23

Ch. 10 (32): The capable project manager provides opportunities for learning and development by encouraging individuals to assume the initiative, take risks, and make decisions.

True

False

4 points

QUESTION 24

Ch 10 (2): The project manager has primary responsibility for_______ in planning, organizing, and controlling the work effort to accomplish the project objective.

a. Doing the paperwork

b. Making all of the decisions

c. Providing leadership

d. Impeding

4 points

QUESTION 25

Ch 10 (7): The project manager reviews the plan with the customer to gain endorsement and then sets up a project management information system for

a. Recording the plan

b. Solidifying the agreement of the plan

c. Comparing actual progress to planned progress

d. Using technology to appear competent

Show more
  • @
  • 177 orders completed
ANSWER

Tutor has posted answer for $18.00. See answer's preview

$18.00

*********

*

**** * group *********** to **** a ******* ** ******* ***** This is ** ******* ** * ******** *****

******

********

2

**

*

***** The

sponsor

provides *** ***** ** ********** *** ******** True ****** QUESTION ** **

*

*****

The

introduction

of

* ***

process

to **** ******** for a **** is an ******* ** * ******* objective True ****** ******** 4 Ch * **** ********* are

identified

and

selected

******

****

* **********

******

b Planning ****** * ********** phase * ******* phase ********

5

** 1 (11):

While

********** **** ***

***

********** ** the

baseline

**** **** be

*********

in accordance

***

* **** *** ****** *********** *** the ******** ***** to *** * ******* ******* **** ******** ********* * ***

***

******* has ********* *** ***** ******** ** *** past d The

project

schedule and technical *************** ******** 6

Ch

2 **** Every ******* **** is ********** ** ******** ** be completed

*****

False 4 points ******** ** Ch 2

(9):

The project

*******

** **** ****** a ******* ************* ** * ******* ********** ********* ***** ******

*

*******

QUESTION

**

**

2 ****

Projects

that are

not

******* cannot ** ******** when ****** * selection ** **** ******* **** a ******** ***** ****** *

*******

********

**

Ch

*

**** **

**********

*** *

************

******* ***** be * *** ********* **** ** construct *** ********* b * ***** **** ** ******* ** **** fund ***

********

*

***

regulations

***

the *****

********

*** ***

*********

d the **** ** *** ******** ** ** ************ * *******

********

*** ** 2 **** *** implementation ** ***

***

procedure ** ******** to ****** ***** ** production ** *** over

***

next **** This ** ** ******* ** *** **************** **

*

******* ******** a ********** ********* * ******* ********** c

*******

************ d

*******

criteria ***

expected

benefits * ******* ******** *** Ch 3 (10): It ** ********* ** submit an *********** ******** ** a ********* ***** ****** * ******* ******** *** Ch 3 ***** * ********** ****** **** *******

**

**** if ****

have

the required resources

*******

** ***** ******

*****

****** * ******* ******** *** Ch

*

***** **

***

*** ******

requirement

****** a **** ***** the customer can ****** * ******** **** ******* *** ****

*****

without

***

*******

*******

True ******

*

******* ********

***

** 3 **** ********* and partner ************* ****** ** work with ****** ***** a **** *** **** ***** **** ****

**********

*

****

***

******

c ****

***

lean companies

****

*** ********** * have **** ****** * ******* ******** *** Ch * **** You *** reading ** ******* ***** ********* ********* *** ******** **** **** **** XYZ

*******

*******

lepidopterology

You

******

to *

****

**** *

****

**** * **** that you thought ** ***** ** ** ******** to ****

*

*** ****** **** ******** ** **** **** already

read

the article * Send

****

a **** ** *** ******* **** * ****

******

*** ********** *** ***

with

the latest

*********

********** *

Print

a **** ** the ******* *** *** it ** **** **** ** case **** ***** ** **** **** * ******* ******** *** Ch

*****

*** ******* scope document defines **** needs ** be done ***** ****** * ******* ******** *** ** 4

****

*** work breakdown ********* *** ******* specifications ********* **** ***** ****** **

performance

********** **** as ***** ****** ********** ********** time ** operating temperature **** the ******* ****** must ******** ***** ****** * points

********

*** ** * (14): * ******* ******* ** a ********* *** ********** *** subdividing *** *** ******* **** *** deliverables

****

**** **********

components

***** False

*

points ******** *** ** 4 ***** Although ***** ** *** deliverables ***

**

******

**

the

project

******* **

*******

for ********

****

**** to ** ___________________ in *** ******* ***** ********* ********* ******** ** in ******* ******* stated at ****** ******* ****** ** ******** **** the *********** ****** ** ************* 4 ******* ******** *** **

*

*****

***

******

**

* *******

that

displays how

all

*** ******** ********** *** together ** accomplish *** ******* **** ****** * work breakdown ********** * ******* scope ********** c ******* ***** d

network

diagram

4

*******

********

*** **

***

***** ***

*******

manager *********** the ********** *** ********** for **** ***** ** ** **** *** **** ***** *** ******* team ******* *** ** *** ** done ***** False * points QUESTION

22

Ch

**

***** *** capable project *******

understands

**** motivates **** *******

***

creates * competitive *********** ** ***** individuals ******* as

part

of a

***************

**** and

are

******** ** ****** ***** False * ******* ******** *** ** ** ***** The capable project ******* ******** ************* *** ******** *** *********** **

***********

*********** ** assume ***

initiative

**** risks and ****

**********

***** ****** *

points

******** *** **

**

(2): ***

*******

manager ***

*******

responsibility for_______ in ******** ********** *** controlling *** work ****** to ********** *** ******* ********** * ***** *** ********** b ****** all ** the decisions * Providing *********** d

*********

*

points

********

***

Ch 10

****

*** *******

*******

******* the **** **** the customer to **** *********** *** **** sets ** * ******* management *********** system **** * ********* *** plan * *********** the agreement of *** ***** * Comparing

******

********

**

*******

*********

* Using

technology

** ******

*********

Click here to download attached files: Fisher college CS400 midterm exam.docx
or Buy custom answer
LEARN MORE EFFECTIVELY AND GET BETTER GRADES!
Ask a Question