Waiting for answer This question has not been answered yet. You can hire a professional tutor to get the answer.

QUESTION

Week 8

Week 8 Discussion 1

COLLAPSE

Overall Rating:

  • 1
  • 2
  • 3
  • 4
  • 5
  • 1
  • 2
  • 3
  • 4
  • 5

“Monitoring Project Performance.” Please respond to the following:  

  • Consider two (2) projects in which you have been involved (work related or personal projects).
  • For each project, identify which of the project monitoring approaches described in the textbook would have been the most appropriate to use in monitoring project performance and describe why.
  • Describe which type of monitoring system was actually used in each of the projects you discussed.
  • Assess how well the system that was used worked for the given project.

Week 8 Discussion 2

COLLAPSE

Overall Rating:

  • 1
  • 2
  • 3
  • 4
  • 5
  • 1
  • 2
  • 3
  • 4
  • 5

“Earned Value.” Please respond to the following:  

  • Using the information provided in Exercise 13 at the end of Chapter 9 in the textbook, calculate the PV, AC, EV, SV, CV, SPI, CPI, TCPI, EAC, and revised duration values for weeks 1–7 for each activity.
  • Assess the managerial implications of the performance results. What short-term adjustments should be made to the project?

Week 8 Discussion 1

COLLAPSE

Overall Rating:

  • 1
  • 2
  • 3
  • 4
  • 5
  • 1
  • 2
  • 3
  • 4
  • 5

“Outsourcing.” Students will respond to the following:

  • With the growth of outsourcing to third-party goods and services at a rate of 40 to 80 percent, how can project managers lead successfully?

    Week 8 Discussion 2

    COLLAPSE

    Overall Rating:

    • 1
    • 2
    • 3
    • 4
    • 5
    • 1
    • 2
    • 3
    • 4
    • 5

    “Statutory Regulations.”

    • What can occur when the project manager fails to comply with statutory regulations?

Show more
LEARN MORE EFFECTIVELY AND GET BETTER GRADES!
Ask a Question